On 10% level;

Petition

Progress payment report prepared by construction inspection authority will be obtained from the internet based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

Invoice original and photocopy (to be returned after witnessing its original)

Bank statement and photocopies

If the construction is over 1000 meter square, bank statement and photocopies of the following progress payment

Technical personnel list assigned by construction inspection authority on the construction site (its original and photocopies based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation)

Construction license photocopy

Construction Inspection service contract photocopy (based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

On 20% level;

Petition

Progress payment report prepared by construction inspection authority will be obtained from the internet based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

Invoice original and photocopy (to be returned after witnessing its original)

Bank statement and photocopies

If the construction is over 1000 meter square, bank statement and photocopies of the following progress payment

Technical personnel list assigned by construction inspection authority on the construction site (its original and photocopies based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation)

Concrete length (Foundation, normal floor column, normal floor tile)

Control minute of formwork and reinforcement production (based on the Law on Construction Inspection no. 4708 and the Annex 8-Form 22 of Construction Inspection Application Regulation)

Concrete casting minute (based on the Law on Construction Inspection no. 4708 and the Annex 9-Form 22 of Construction Inspection Application Regulation)

Concrete pressure strength reports (graphical results, 7 and 28 daily test results)

Iron length (for whole construction)

Reinforced concrete steel bar testing report

Iron sampling minutes

Foundation surface and iron visa have been acquired

On 60% level;

Petition

Progress payment report prepared by construction inspection authority will be obtained from the internet based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

Invoice original and photocopy (to be returned after witnessing its original)

Bank statement and photocopies

If the construction is over 1000 meter square, bank statement and photocopies of the following progress payment

Technical personnel list assigned by construction inspection authority on the construction site (its original and photocopies based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation)

Control minute of formwork and reinforcement production (the Law on Construction Inspection no. 4708 and the Annex 8-Form 22 of Construction Inspection Application Regulation)

Concrete casting minute (based on the Law on Construction Inspection no. 4708 and the Annex 9-Form 22 of Construction Inspection Application Regulation)

Concrete pressure strength reports (graphical results, 7 and 28 daily test results)

Reinforced concrete steel bar testing report

Iron sampling minutes

On 80% level;

Petition

Progress payment report prepared by construction inspection authority will be obtained from the internet based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

Invoice original and photocopy (to be returned after witnessing its original)

Bank statement and photocopies

If the construction is over 1000 meter square, bank statement and photocopies of the following progress payment

Technical personnel list assigned by construction inspection authority on the construction site (its original and photocopies based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation)

Architectural, electrical, sanitary installation control minutes

Petition for heating insulation and rough construction visas

Heating insulation and rough construction visas are performed.

On 95% level;

Petition

Progress payment report prepared by construction inspection authority will be obtained from the internet based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

Invoice original and photocopy (to be returned after witnessing its original)

Bank statement and photocopies

If the construction is over 1000 meter square, bank statement and photocopies of the following progress payment

Technical personnel list assigned by construction inspection authority on the construction site (its original and photocopies based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation)

On 100% level;

Petition

Work completion certificate (3 copies)

Progress payment report prepared by construction inspection authority will be obtained from the internet based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation.

Invoice original and photocopy (to be returned after witnessing its original)

Bank statement and photocopies

Technical personnel list assigned by construction inspection authority on the construction site (its original and photocopies based on the Law on Construction Inspection no. 4708 and the Annex 24-Form 22 of Construction Inspection Application Regulation)